Languages homework help

Use the table below  to answer the following questions: Which activities are on the critical path?What is the duration of the project?Which activity has the most start slack?Activity IDPredecessorTimeA*None8B*None4C*None7DB5EA,D4FC,D3GE2HE3IF5JH,I2KG,J3

 